NEWS

Progress at Cedar House

January 24, 2013

Construction on the renovation of Cedar House commenced in August 2012. Works involved a sustainable renovation of a Grade II listed 1960’s property. It is one of only a few 1960’s houses that have been afforded such protection. Works involved the complete internal renovation of the property coupled with extensive sustainability works to achieve almost Passiv Haus standards.  The project is due to complete end of February. The construction process has been both interesting and challenging, implementing a detailed design to achieve such a high standard as Passiv Haus. Our clients have worked closely with Trunk – Environmental Consultants, at the beginning and throughout the project.

 

New Contract Awarded

September 30, 2012

We are delighted to confirm that we have recently secured a new contract for the renovation of a Victorian property in the centre of Oxford. The ambit of works include second and ground floor extensions along with the addition of a large basement. Works are to commence shortly.

New Contract Awarded

September 30, 2012

We are delighted to confirm that work has commenced on a new contract for the restoration of a 1960’s listed property. The works include a highly specified thermal upgrade to near Passiv Haus standards. Images to follow.

Software Update

September 30, 2012

Our apologies for being unable to update progress on our current projects over the last few months. We have been expanding our design software.

Progress at Oak Manor

May 30, 2012

Phase 1 is nearing completion. Our extensive Q & A Procedures are now being undertaken prior to decoration. The demolition of the existing building is due to take place at the start of July with the construction of Phase 2 to commence shortly thereafter.

Progress at Hazel Terrace

May 30, 2012

Roofing to existing house is now complete along with the refurbishment of the sash windows. Plastering to the main house and waterproofing to the basement is nearing completion.

Progress at Oak Stable

May 30, 2012

Masonry alterations to phase 1 are now complete. Roof covering to barn 2a is complete and underway on the remaining barns. First fix M & E has recently commenced. We are delighted to have been awarded the contract for phase 2 of this project.